Preview Preview: 9,085 permits loaded from Chicago, Austin and Seattle. More cities are being added. Sourced from city open-data portals. Data as of 2026-09-07.

Chicago · permit 101087678

1401 S SACRAMENTO DR

PERMIT EXPIRES ON 10/27/2026 ERECTION STARTS: 9/9/2026, ERECTION ENDS: 9/23/2026. CBC2019 - PEER REVIEW - REINSTATEMENT OF 2025 RIOT FEST DOUBLE STAGE PERMIT 101073628 AT DOUGLASS PARK FOR THE 2026 RIOT FEST DOUBLE STAGE ON SEPT 18-20, 2026 WITH SETUP SEPT 9 AND TAKEDOWN SEPT 23, 2026. SAME 1- 252FT X 64FT DOUBLE STAGE WITH SOUND TOWERS. RIOT FEST CORP. WITH BIGTENT EVENTS.

Permit type
PERMIT - NEW CONSTRUCTION
Status
ACTIVE
Applied
2026-08-25
Issued
2026-08-27
Contractor
DAVID SPATA BIGTENT EVENTS, INC
Declared value

Data as of 2026-09-07.