Preview 555,290 permits — every permit Chicago, Austin and Seattle issued in the last ten years. The full load is in progress, so this is how far it has got. Sourced from city open-data portals. Data as of 2026-09-21.

Abode Modern Homes

Austin, TX

30 Permits on record
17 Addresses
4 Permit types

Permits issued between 2016-09-28 and 2023-02-24.

How long the city took

Days from application to issue, by permit type, with the city's own median for the same type beside it. This measures the permit office as much as the contractor.

Permit typePermitsMedian daysAustin medianSlowest 10%
Plumbing Permit3542 40658
Driveway / Sidewalks11533 146780
Building Permit15129 22175

What they pull permits for

Trades

ValuepermitsShare
General/Building 15
Other 11
Plumbing 3
Electrical 1

Nature of work

ValuepermitsShare
New 21
Demolition 4
Other 2
Addition 2
Alteration 1

Where they stand

ValuepermitsShare
Final 29
Withdrawn 1

Where they have worked

17 addresses. Most recently permitted first.

Every permit above is published by the City of Austin in its open-data portal. 555,290 permits — every permit Chicago, Austin and Seattle issued in the last ten years. The full load is in progress, so this is how far it has got.